Pune Ring Road Project Costs Soar Amid Scrutiny Report Delays

The Maharashtra State Road Development Corporation (MSRDC) is facing delays in receiving a crucial third-party scrutiny report for the tenders related to the Pune district’s ring road project. Despite three weeks having passed since the scrutiny process began, the report’s absence has heightened concerns about the integrity and cost of the tender process.

Project Overview

The Pune Ring Road project is an ambitious initiative aimed at alleviating traffic congestion in Pune and Pimpri-Chinchwad. The project spans 127 kilometers in length and 110 meters in width, divided into East and West phases. The MSRDC is overseeing this significant infrastructure development.

Tender Process and Submissions

The tender process attracted twelve submissions from contractors bidding across nine phases of the project. During the bid opening in Mumbai, Megha Engineering & Infrastructures Limited and Navayuga Engineering Company Limited emerged as the lowest bidders for six packages (three each). PNC Infratech Limited, Roadway Solutions India Infra Limited, and G R Infraprojects were identified as the lowest bidders for the remaining three packages.

Issues of Inflated Tenders

Several companies involved in the election bond scandal submitted tenders at inflated rates, complicating the process further. The scrutiny revealed that the bids were 40-50% higher than MSRDC estimates, potentially increasing the project’s cost by 1.5 times. Initially projected at Rs 16,000 crore, the project’s cost has now escalated to Rs 22,000-23,000 crore due to these inflated tenders.

Delayed Scrutiny Report

The technical institute responsible for scrutinizing the tenders has not yet delivered its report, despite the scrutiny process starting three weeks ago. An anonymous MSRDC official confirmed the delay, exacerbating concerns about the tender process’s transparency and efficiency.

Potential Implications

The acceptance of these inflated bids could lead to significant cost overruns and potential disputes. On the other hand, re-tendering the project might delay its completion by three to six months, adding another layer of complexity to the situation. This issue is expected to be a focal point in the ongoing monsoon session of the Maharashtra Legislative Assembly, where it will likely spark considerable debate.

Key Concerns

  1. Overestimated Costs: The scrutiny revealed bids that were 40-50% higher than MSRDC estimates, raising the project’s cost by approximately 1.5 times.
  2. Delayed Scrutiny: The third-party scrutiny report, critical for assessing the validity and fairness of the bids, is still pending despite the process beginning three weeks ago. This delay is causing significant concern among stakeholders.
Share this article
0
Share
Shareable URL
Prev Post

Pune: Sant Tukaram Maharaj’s Palkhi to Start Journey; Dehu Abuzz with Devotees, CM Shinde to Attend

Next Post

Rising Temperatures: Protecting Workers Amid Record-Breaking Heat

Read next
Whatsapp Join