Pune Metro Expansion Gains Momentum: Maha Metro Initiates Bidding for PCMC to Nigdi Metro Extension

In a significant move towards enhancing Pune’s metro connectivity, the Maharashtra Metro Rail Corporation Limited (Maha Metro) has officially opened bids for the construction of a 4.5 km elevated viaduct between Pimpri-Chinchwad Municipal Corporation (PCMC) and Nigdi on the North-South Corridor—Pune Metro Reach 1 Extension.

Key Details of the Metro Extension Project:

  • Completion Period: The project is expected to be completed in 130 weeks from the date specified in the Letter of Award (LOA).
  • Document Availability: Interested parties can download bid documents from 16th December 2023, 16:00 pm, to 22nd January 2024, 16:00 pm, from the Maha-Metro e-tender portal.
  • Cost of Document: The cost of the bid document is INR 1,18,000 (One Lakh Eighteen Thousand only), inclusive of applicable GST. The amount is non-refundable and payable through e-payment methods like Credit Card, Debit Card, or Net Banking, following the procedure outlined in the tender document.
  • Pre-Bid Meeting: A pre-bid meeting is scheduled for 9th January 2024, 11:00 am, at the office of ED/Procurement, Maha-Metro. Queries can be submitted via email or in hard copy before the stipulated date and time.
  • Bid Security (EMD): Bid Security or Earnest Money Deposit (EMD) of INR 1.74 Crores (One Crore Sixty-Six Lakhs Only) is required, to be submitted in the form of an Irrevocable Bank Guarantee as specified in the tender document.
  • Tender Submission: The deadline for online submission of tenders is 22nd January 2024, 16:00 pm, on the Maha-Metro e-tender portal.
  • Tender Opening: The opening of tenders will take place on 22nd January 2024, after 16:30 pm, at the Procurement Department, Civil Court Metro Tender Station, Pune.

To access the tender notice (NIT) and additional details, interested bidders can visit the Maha-Metro website www.punemetrorail.com or the CPPP portal https://eprocure.gov.in.

For the complete e-payment procedure, submission guidelines, and other specifics, visit the Maha-Metro tender portal at https://mahametrorail.etenders.in.

The responsibility for all costs related to bid preparation and submission lies with the bidder, and Maha-Metro will not be accountable for these costs, irrespective of the bidding process’s outcome.

Share this article
0
Share
Shareable URL
Prev Post

Palestine, US reach agreement to resolve PA funds held by Israel: Source

Next Post

Bengaluru SG Mavericks Triumph in Tennis Premier League Season 5 Grand Finale

Read next
Whatsapp Join