Mumbai Airport to Begin Construction on T1-T2 Underground Tunnel Post-Monsoon

Mumbai International Airport Ltd (MIAL) is set to commence the construction of an underground tunnel connecting the T1 and T2 airsides of Chhatrapati Shivaji Maharaj International Airport (CSMIA). The project, which has been in the planning stages for several years, is expected to cost between Rs 500-600 crore and take 12-16 months to complete. Work is scheduled to begin after the monsoon season.

Project Overview

The underground tunnel will be a three-lane passage running beneath both cross runways of the airport. It will facilitate the airside transfer of passengers, baggage, cargo, and ground support staff. The project will be carried out in two phases, starting with drilling from T2 to the south side and then extending to T1.

Phased Construction Plan

The construction process will be phased to minimize disruptions:

  • Phase 1: Drilling and construction from T2 towards the south side of the airport.
  • Phase 2: Extending the tunnel from the south side to T1.

Infrastructure Enhancement

This development is part of a broader effort to enhance the infrastructure at CSMIA, especially in light of the impending opening of the Navi Mumbai International Airport (NMIA) by March next year. Upon NMIA’s completion, various facilities, including hangars, cargo, and general aviation, will be relocated from CSMIA to NMIA. This relocation will allow for additional aircraft parking stands and the demolition of T1 to build a new terminal.

Waterlogging Prevention Measures

To prevent waterlogging in the tunnel, MIAL, in collaboration with the Brihanmumbai Municipal Corporation (BMC), is working on improving the nullah that connects to the Mithi River. This is crucial for ensuring the tunnel remains operational during heavy rains.

Project Delays and Renewed Momentum

The tunnel project was postponed multiple times, initially due to the COVID-19 pandemic, which severely impacted air travel and led to the deferment of several capital projects. The Adani Group’s acquisition of MIAL in 2021 provided renewed momentum for the project, aligning it with ongoing efforts to expand CSMIA’s infrastructure.

Timeline and Contingencies

While detailed plans are still being finalized, MIAL has indicated that the tunnel work will begin this year, contingent upon the severity of the monsoon season. The construction of the underground tunnel linking T1 and T2 at Mumbai’s Chhatrapati Shivaji Maharaj International Airport marks a significant step in enhancing airport infrastructure. This project will improve airside connectivity and streamline operations, especially as the region prepares for the operationalization of Navi Mumbai International Airport.

Share this article
0
Share
Shareable URL
Prev Post

Rajiv Gandhi Infotech Park to Get Advanced Waste Processing Facility

Next Post

Maharashtra Prepares for Monsoon with Increased Dengue Surveillance

Read next
Whatsapp Join